Above: Workers have been restoring downtown Olympia’s Fourth Avenue bridge for about ten weeks. The bulk of the project involves cleaning and painting, however, some repairs are also being done. The project is being funded out of the City of Olympia's transportation general fund for $451,962.
By
Janine Gates
Little Hollywood
For the past ten weeks, thousands of commuters have
watched a crew at work on the Fourth Avenue bridge
in downtown Olympia.
Formally known as the Olympia-Yashiro Friendship
Bridge, the bridge spans Budd Inlet, the southernmost portion of Puget Sound.
A critical east-west transportation link for the city, the bridge symbolically connects the Olympia community in many other ways as well.
A critical east-west transportation link for the city, the bridge symbolically connects the Olympia community in many other ways as well.
While the bulk of the project involves cleaning and
painting, some crack repair is also being done to prevent future water
intrusion. Water damage causing significant pockmarks and spalling of cement pieces has occurred in about 250 feet of the bridge.
A contract amount of $451,962 was given to Finishing
Touch Masonry and Restoration Solutions, LLC, of Everett.
The project is considered a transportation project
and is being funded out of the city’s transportation general fund.
“This project was not bid per our typical design-bid
build process however it is a U.S. Communities project and these types of
projects meet the competitive bidding requirements,” said Jeff
Johnstone, project manager and senior engineer with the City of Olympia, when asked about the cost.
The U.S. Communities Project is a partnership formed
in 2009 among the U.S. Housing and Urban Development, the U.S. Department of
Transportation, and the U.S. Environmental Protection Agency.
The city’s use of
U.S. Communities was approved by city council in 2016.
Johnstone added that after the work is complete, the bridge will retain its shiny white appearance, and should only need to be pressure washed once a year.
“I never realized how grubby it had gotten until I saw side by side pictures,” said Johnstone.
Prior to construction of the bridge, Johnstone said that the city tested multiple different coating products.
“These products were applied to concrete panels and
allowed to sit for the winter in order to determine how well they held up to
our winter conditions and how easy they were to clean. Graffiti testing was
also conducted on each coating. The coating being used was selected because it
is a single step coating process and once the coating container is
opened, it can be resealed and saved for later use, similar to a can of paint,”
he said.
Above: The Olympia-Yashiro Friendship Bridge, better known as the Fourth Avenue bridge, spans Budd Inlet, the southernmost tip of Puget Sound.
Workers interviewed on Tuesday were disappointed
that their completed work on the south side of the bridge has already been
tagged with graffiti.
“It takes a couple minutes to tag, but takes a
lot more time than that to clean it off,” said Rick Schindler, a restoration
mason and project foreman with Finishing Touch Masonry.
Schindler, of Everett, has been busy with Ken
Hester, of Shoreline, to brush, hand scrape, seal, vacuum, and pressure wash
the bridge. He recently hired another employee to speed up the work and says he
hopes to get the project done by the end of September.
Schindler explained that the westernmost 250 feet of
the bridge between the roundabouts on Olympic Way has
the most water intrusion damage because the concrete was poured onsite, which
resulted in a very difficult finish.
Workers at the time realized their mistake, Schindler
said, and used precast forms for the rest of the bridge.
“Those look a lot better,” he said.
“It’s been a tedious project to get right,” said
Hester.
All workers are Pacific Northwest chapter members of
the International Union of Bricklayers and Allied Craftworkers.
A
Brief Bridge History
The bridge was completed in 2003 to replace the previous
bridge which was structurally damaged in the Nisqually based earthquake on
February 28, 2001.
The earthquake speeded up a bridge replacement process that
was already underway, as load
limits had already been placed on the bridge.
Former City of Olympia Mayor Bob Jacobs was asked
about his involvement in the planning for the new bridge in the late 1990s prior
to the earthquake.
“The previous bridge lasted as long as it did because it had been constructed with extra strength to carry trolley traffic.
“The previous bridge lasted as long as it did because it had been constructed with extra strength to carry trolley traffic.
“It was generous of the council to include on the bronze plaques all of
the names of council members who participated in the entire, long planning process. It’s a great looking bridge. Although the cost estimates
had to be increased several times, our council made detailed decisions on the
design of the bridge, including the number of lanes, width of sidewalks, and
height of railings.
“Partway into the process, it was decided to expand
the project to include the area to the west and call it the Olympia Gateway
Project. The roundabouts were a big risk because such
structures were rather new at the time and the slopes made them difficult to
construct. All in all, it turned out very well,” said Jacobs.
Editor's Note, August 24: Little Hollywood deleted a previously published statement that the Fourth Avenue bridge never had trolley traffic.
Editor's Note, August 24: Little Hollywood deleted a previously published statement that the Fourth Avenue bridge never had trolley traffic.
Above: Olympians braved the rain to celebrate the grand reopening of the Fourth Avenue Bridge in December, 2003. The bridge serves as a critical east-west transportation link in Olympia. The Nisqually earthquake made the previous bridge unusable, causing over two years of inconvenience for commuters.